How often should a lender refresh site photos between draws?

Most construction loan servicing shops answer this question the same way: site photos get refreshed when the inspector shows up for the draw. Draw comes in, inspector drives out, photos go in the file. Next refresh is whenever the next draw request lands, which on a typical schedule is three to five weeks later.
That cadence was set by the draw schedule, not by how fast the site changes. For a lot of projects, especially anything in the frame-to-dry-in stretch, three to five weeks is long enough for a lot to happen between looks.
What sets the default cadence
Draw frequency on most construction loans runs monthly, sometimes every six weeks on smaller deals or slower-moving commercial projects. The inspection that accompanies each draw request exists to answer one question: does the work in place match what the contractor is billing for. That check happens on the draw calendar. The gap between inspections is set by the loan documents, not by the risk level on site at any given moment.
A few things make the monthly default thinner than it sounds:
- A contractor's percent-complete number on a draw request is self-reported. The inspection is supposed to confirm it, but one site visit a month means the lender's only cross-check happens right when the money is about to move, not before.
- Weather days, subcontractor no-shows, and material delays don't wait for the draw date. A project that looked on-track at the last draw can lose two weeks of schedule before anyone outside the job site knows.
- The riskiest phases of a build (foundation, framing, dry-in) often move fastest and are also the phases where a missed problem is most expensive to unwind later.
None of that means draws need to happen more often. It means the photo record between draws doesn't have to be tied to the draw at all.
Why monthly leaves a gap
Think about what a lender actually has on file between draw dates under the standard monthly cadence: nothing. No photo, no notes, no independent record of what the site looked like in week two or week three. If a dispute comes up later, over a change order, a delay claim, or a draw that got approved against work that turned out to be behind, the file has a photo from draw four and a photo from draw five and a five-week blank spot in between.
A weekly cadence closes that gap without changing anything about how draws get processed. The draw schedule stays monthly. The photo record just stops being tied to it. A weekly drone capture for construction loans gives the lender a photo and a percent-complete reading for every week of the project, not just the weeks a draw request happened to fall on. If something goes sideways between draws, there's a record showing when it started, not just a before-and-after that spans a month.
Matching draw inspection frequency to the record, not the other way around
The cleanest way to think about this: draw inspection frequency can stay exactly what the loan documents say. The site photo cadence doesn't have to match it. Keep the formal inspection on the draw schedule for the billing check. Keep the photo record on a tighter, independent cycle so there's something to compare the draw request against when it arrives, instead of taking the contractor's word for where things stood the week before.
That's the gap Construction Progress was built to close: a weekly drone pass measured against the project schedule, turned into a progress map a loan officer can set beside the draw request instead of relying only on the number the contractor sent in.
If a draw request has ever landed on your desk and you had no way to check it against what the site looked like three weeks earlier, a weekly capture is worth a look.